North West Electrification (NWEP) Phase 2

August 2014 - July 2015

£1.8m

Liverpool to Manchester

Download full PDF case study

Pod-Trak was approached by Balfour Beatty Rail in July 2014 to assist with the installation of new OLE on the Liverpool to Manchester and Liverpool to Wigan routes.

The series 2 equipment was supplied free issue by BBR and installed by Pod-Trak teams working on our RRV MEWPs. Core works included SPS installation, wiring and final registration.

Critical tie-ins to existing electrification at Edge Hill and the West Coast Mainline were all carried out by Pod-trak. All plant moves between sites were managed and carried out in-house.