Follow us on Social Media:

West Coast Main Line PSU

July 2014 - January 2018

£4.6m

West Coast Main Line

Download full PDF case study

ATF works on the West Coast Mainline power supply upgrade (PSU) project utilising weekend possession/isolations in the North and midweek possession/isolations in the South.

Supply of OLEC staff and RRV MEWPs to support the works, including all transport required to move between the northern and southern sections of the project. Works included the installation of SPS, feeder wire, switching, assisting with the testing & commissioning and the removal of redundant equipment.

Other case studies

Ilford Crossrail Depot – OLE

Metrolink 2CC

Sussex 7-Day Railway Hookswitch Replacement Project