Follow us on Social Media:

Anglia Structures (OLE)

Anglia OLE
Railway Electrification

MARCH 2017 – SEPT 2017

£750K

ANGLIA

Download full PDF case study

Key Information

Replacement of 24 existing structures with new single cantilever arrangements

Contract value of £750,000

Situated in East Anglia

Network Rail identified a number of Overhead Line Equipment (OLE) structures throughout the Anglia region with varying degrees of lean, and as such all needed to be renewed to reduce the risk of OLE failure.

Pod-Trak’s extensive experience in OLE works meant that it was the contractor of choice to ensure that these structures remained reliable through improvements in longevity and a reduction in wear and tear.

The lean is caused by several factors including poor ground conditions, inadequate foundations, steelwork damage and life expired equipment. The scope of works on this phase of the project was the replacement of 24 existing structures with new single cantilever arrangements.

The works involved the installation of:

  • New OLE pile foundations
  • New structures
  • New cantilevers
  • New droppers
  • New midpoint anchors
  • New registration

It also included the installation and alteration to Return Conductor wires and removal of the redundant structures.

All works were carried out over a series of weekend possessions carried out as follows:

  • Install 610mm piles
  • Install main steel & bonding (both temporary and permanent bonding)
  • Install Small Part Steel (SPS)
  • Transfer of OLE and new registration
  • Install / move return conductor wire to new Design
  • Removal of redundant steel

Post works all associated hand back material was submitted supporting the installation including:

  • Quality Check Sheets
  • Redline drawings
  • Height and stagger surveys

Other case studies

Manchester Metrolink - Overhead line equipment

Overhead Line Equipment – Manchester Metrolink Phase 3

Swansea Maliphant Intercity Express Depot (Hitachi)

Manchester Metrolink Substations