Crossrail Western Outer Electrification

Railway Electrification

APRIL 2016 – JUNE 2017

£5.6M

MAIDENHEAD (WEST LONDON)

Download full PDF case study

Key Information

Installation of main steel, SPS, wiring and final registration

Contract completed over one year

Completed in Maidenhead and West London

The Crossrail Western Outer OLE Project provided Electrification of the outer Crossrail route between Stockley Junction to West of Maidenhead station. The Project included electrification of the Main lines, Relief lines, Crossovers, Loops, Sidings and Turn-backs.

Pod-Trak provided Construction Management, Engineering, OLEC teams, OTP and POS to assist Balfour Beatty with the works. The overall scheme consisted of the detailed design, construction, test and commission of a Series 1 Furrer & Frey system.

To assist with the daily planning and delivery of the project, Pod-Trak provided Construction Management and Engineering to manage OLE teams, work site integration, material management and assurance/handback documentation.

The site teams working alongside Balfour Beatty teams and other suppliers, installed main steel, SPS, wiring and final registration.

With adjacent lines open to traffic all plant had to be ALO compliant. This was managed nightly by Pod-Trak POS Representatives working closely with the Balfour Beatty ALO coordinators.