July 2014 - January 2018

£4.6m

West Coast Main Line

Download full PDF case study

ATF works on the West Coast Mainline power supply upgrade (PSU) project utilising weekend possession/isolations in the North and midweek possession/isolations in the South.

Supply of OLEC staff and RRV MEWPs to support the works, including all transport required to move between the northern and southern sections of the project. Works included the installation of SPS, feeder wire, switching, assisting with the testing & commissioning and the removal of redundant equipment.