Elmers End Loop – Croydon Tramlink

Elmers End Loop

May 2012 - July 2012

£150k

London

Download full PDF case study

At Elmers End Loop on the Croydon Tramlink an existing siding was converted to a passing loop.

Pod-Trak undertook the OLE installation works which included new structures, SPS and wiring along with alterations to existing infrastructure.

Prior to any trams using the new line, all handover checks were completed including panning and height and stagger recordings. Finally, the new installation was tested and commissioned by Pod-Trak prior to entry into service.