Widow Hill – BESS Substation Civils Delivery

Project Overview

Pod-Trak was appointed to complete the civil engineering works for the Widow Hill BESS substation in Burnley, taking over an existing site from a previous subcontractor and progressing the outstanding works to Suir Engineering’s programme and quality requirements.

The works formed a new M&E infrastructure compound supporting wider network upgrades and enabling the subsequent installation and commissioning of electrical infrastructure for Electricity North West.

Quick Facts

Client Name
Suir Engineering
Project Location
Burnley, North West England
Project Duration
2 Months

High Level Scope:

  • Reinforced concrete foundations for a range of electrical assets across the compound.
  • Cable ducting infrastructure and precast concrete cable troughing.
  • New Electricity North West substation building, drainage, earthworks and backfilling.
  • Earthing-system attendance support, including excavation and cable connections.
  • Additional cable and DNO works, including HDD exposure pits, trenches, cable-pulling attendance, reinstatement, slabs and doors.
  • DNO building painting and the final lighting-column foundation.

Key Challenges & Solution

Sequencing the 35 reinforced concrete plinths while retaining excavator and dumper access to rear earthworks was a key challenge. Building the entrance plinths first would have restricted plant manoeuvrability and created programme risk.

Pod-Trak agreed a phased sequence with the client that kept a continuous plant access route and aligned with commissioning handovers. Earthworks, geotextile and backfilling could therefore progress alongside concrete works, reducing downtime and remobilisation, lowering damage risk and improving safety and programme certainty. No accidents or incidents were recorded.

Innovation in Action

  • Phased construction of 35 plinths to preserve access and maintain workflow across the compound.
  • Parallel earthworks, geotextile installation and backfilling rather than waiting for all concrete works to finish.
  • Reduced plant movements in confined areas, improving safety and protecting completed assets.
  • Close coordination with Suir Engineering and the electrical subcontractor to integrate additional earthing, cable and DNO works.

Images & Media

Explore More Projects

Want to see how we can deliver similar solutions? Browse our other case studies or get in touch with us today.