Pod-Trak was appointed to complete the civil engineering works for the Widow Hill BESS substation in Burnley, taking over an existing site from a previous subcontractor and progressing the outstanding works to Suir Engineering’s programme and quality requirements.
The works formed a new M&E infrastructure compound supporting wider network upgrades and enabling the subsequent installation and commissioning of electrical infrastructure for Electricity North West.
Sequencing the 35 reinforced concrete plinths while retaining excavator and dumper access to rear earthworks was a key challenge. Building the entrance plinths first would have restricted plant manoeuvrability and created programme risk.
Pod-Trak agreed a phased sequence with the client that kept a continuous plant access route and aligned with commissioning handovers. Earthworks, geotextile and backfilling could therefore progress alongside concrete works, reducing downtime and remobilisation, lowering damage risk and improving safety and programme certainty. No accidents or incidents were recorded.
Want to see how we can deliver similar solutions? Browse our other case studies or get in touch with us today.