The Victoria Phase 5 upgrade is a design-and-build project delivered on behalf of Alstom through GRIP 4-8 under CP6. Pod-Trak was contracted to deliver the civil assets required for the re-signalling scheme, from GRIP 4 development through AFC and final As Built information.
The programme covers signal structures, location and equipment bases, route works and associated access planning across a complex operational railway environment.
All investigation and construction access had to be developed around Network Rail’s pre-defined access schedule. Pod-Trak’s in-house planning team coordinated midweek night RotR access, disruptive weekend possessions and non-possession working under ALO.
Coordination and de-confliction workshops, box planning, whiteboards and planning meetings were used to ensure each work package was robustly planned and briefed without creating additional disruption to the travelling public.
Victoria Phase 5 demonstrates Pod-Trak’s integrated design, planning and civil engineering capability for complex re-signalling programmes in constrained operational railway environments.