Sonning Embankment – Landslip Reinstatement Works

Project Overview

In May 2024, Pod-Trak were engaged by Balfour Beatty Rail to assist with the emergency reinstatement of a landslip at Sonning, Berkshire. A substantial section of the embankment had failed, obstructing the railway and disrupting services. Although train operations were quickly restored, a complex civil engineering solution was required to stabilise the slope and reinstate long-term integrity while maintaining live traffic.

Working collaboratively with Balfour Beatty and Network Rail, Pod-Trak’s experienced civil engineering team delivered a safe, efficient, and innovative programme of stabilisation works under constrained access conditions.

Quick Facts

Client Name
Balfour Beatty Rail (BBR)
Project Location
Sonning, Berkshire, UK
Project Value
£2m

High Level Scope:

  • Installation of temporary access ramp into the embankment for safe plant movement.
  • Removal of 5,000 tonnes of slipped material using tracked excavators and RRVs.
  • Construction of a shear key and stepped slope with reinforced geotextile and stone fill.
  • Installation of counterfort drains and improved surface drainage.
  • Sheet piling works – 30 m of PU28 piles (5 m long) with pre-augering and EMV installation.
  • Construction of key clamp fencing and permanent slope protection.
  • Full logistical management for materials delivery, spoil removal, and stakeholder coordination.

Key Challenges & Solution

Access to the site was extremely limited and adjacent to a live railway and local businesses. Pod-Trak developed an access road cut into the embankment, enabling safe movement of excavators and dumpers while maintaining slope stability.
Night-time possessions were used for RRV removal of trackside material, while daytime operations focused on re-profiling and drainage installation.

During works on the south embankment, a secondary failure occurred on the opposite slope. Pod-Trak immediately mobilised an additional team, working on both sides simultaneously to clear debris and reopen the line.

The permanent stabilisation design included sheet piling tied back with soil nails, stepped slope profiling, and full geotextile coverage compacted with 6G material to restore long-term stability.

Innovation in Action

Pod-Trak delivered innovation in action through a coordinated, dual-site mobilisation strategy that allowed parallel working and the swift reopening of both lines. By adopting a pre-augered piling method, the team effectively reduced vibration and safeguarded the surrounding track infrastructure, while carefully planned logistics ensured smooth spoil removal and material delivery despite the constrained environment. Durability was further strengthened through the integration of counterfort drainage and reinforced geotextile systems. Throughout the programme, our close collaboration with Balfour Beatty and Network Rail, combined with a blend of track possessions, daytime works, and a continuous 24/7 schedule, ensured the project was delivered safely and to a high standard – exemplifying a proactive, disciplined, and quality-driven approach.

Images & Media

Explore More Projects

Want to see how we can deliver similar solutions? Browse our other case studies or get in touch with us today.