Palmersville – Subway Installation

Project Overview

Pod-Trak delivered the installation of a new concrete subway beneath the live railway at Palmersville, near Newcastle upon Tyne.
The project formed part of a wider rail infrastructure upgrade, providing a safe pedestrian and service crossing under the existing tracks while maintaining the integrity of the operational railway.

The works involved complex civil engineering, including major earthworks, drainage, structural preassembly, and precision installation of large precast subway sections during a 5-day blockade.

Quick Facts

Client Name
Morgan Sindall
Project Location
Palmersville, Newcastle upon Tyne, UK
Project Value
£2.5m

High Level Scope:

  • Earthworks and Access Construction:
    • Excavation and profiling of new approach ramps
    • Slope battering, subgrade compaction, and formation build-up
    • Construction of large compound and laydown area
  • Precast Subway Assembly:
    • Delivery and preassembly of precast concrete subway sections
    • Stitching of joints using in-situ concrete pours and Macalloy bar tensioning
    • Structural integration of wing walls and waterproofing
  • Installation Under Blockade:
    • Removal of track and excavation of existing embankment
    • Foundation preparation and formation testing
    • Jack-up and SPMT (Self-Propelled Modular Transporter) installation of subway units
    • Controlled lowering and final alignment of all sections
    • Track drainage installation and backfill to underside of new track
  • Reinstatement Works:
    • In-situ waterproofing, backfilling, and compaction
    • Track reinstatement and handback to Network Rail
    • Drainage connections at track and subway level, including deep tie-in to local sewer
    • Completion of new access road surfacing and fencing

Key Challenges & Solution

Tight possession window: The 5-day blockade required extensive preassembly and precision sequencing, enabling full installation and reinstatement without overrun.

Restricted site access: Temporary ramps and laydown areas were constructed to manage safe logistics for heavy lifting and material deliveries.

Heavy structural handling: Use of SPMTs and hydraulic jacking systems ensured safe, controlled installation of the precast units under live OLE and in proximity to existing infrastructure.

Deep drainage interfaces: Works required liaison with the local authority to manage deep sewer connections and ensure compliance with environmental regulations.

Innovation in Action

Pod-Trak maximised efficiency and safety through extensive off-track pre-assembly, completing all structural alignment, tie-bars, and grouting ahead of the blockade to significantly reduce possession time. Precision SPMT installation allowed heavy units to be placed with millimetre accuracy while minimising ground disturbance. An integrated drainage system was designed to connect the new subway sump with the existing network, preventing future maintenance clashes and ensuring long-term reliability. Throughout the programme, close collaborative planning with the client and Network Rail ensured every activity aligned with critical possession requirements and handback criteria — demonstrating a highly coordinated, forward-thinking approach to delivery.

Images & Media

Explore More Projects

Want to see how we can deliver similar solutions? Browse our other case studies or get in touch with us today.