Orient Way – Drainage Works

Project Overview

Pod-Trak was appointed as specialist Principal Contractor to deliver multi-discipline infrastructure upgrades at Greater Anglia’s Orient Way Traincare depot. The depot had to remain fully functional on a 24/7 basis while obsolete and failing infrastructure was renewed to support the introduction of new rolling stock.

The project ran from April 2023 to December 2024 and required civil, mechanical and electrical works to be phased through a live operational depot.

Quick Facts

Client Name
Greater Anglia
Project Location
London, UK
Project Duration
4 Months

High Level Scope:

  • GRIP 5 AFC review to identify design discrepancies, value engineering opportunities and constructability issues.
  • Removal of redundant storage buildings, cabins, concrete ramps, GRP access platforms and existing CET equipment.
  • New M&E containment, CET pipework and cabling, lighting columns, illuminated bollards and support foundations.
  • New and strengthened GRP walkways, driver access hop-ups and front-end cleaning drip-tray installations.
  • Sanding silo and facility building works, pump-house mechanical/electrical upgrades and control systems.
  • Depot signage, asset labelling and as-built structural gauging clearance surveys using Laser Sweep.

Key Challenges & Solution

Early in the project, Pod-Trak identified significant GRIP 5 AFC design shortfalls, assumptions and compliance issues. These had to be resolved without compromising a tightly controlled possession and depot-operational programme.

The management team worked closely with Greater Anglia and the design team to close out deficiencies, manage interfaces and maintain the accepted programme while keeping the depot operational.

Innovation in Action

  • Phased delivery around pre-planned depot possessions and key access dates.
  • Used regular client and design-team meetings to resolve buildability and design-scope gaps before they affected delivery.
  • Engaged specialist suppliers and consultants with established knowledge of the Orient Way depot.
  • Captured lessons learned on assurance resource, documentation and early compliance checks to reduce future rework.
  • Orient Way demonstrates Pod-Trak’s ability to manage complex multi-discipline upgrades in a live depot, resolving design issues while maintaining safe railway operations and programme control.

Images & Media

Explore More Projects

Want to see how we can deliver similar solutions? Browse our other case studies or get in touch with us today.