Botley Road – Bespoke Temporary Cable Bridge Works

Project Overview

Pod-Trak was engaged by Kier to deliver bespoke temporary cable bridges as part of the Botley Road Bridge Replacement at Oxford Station. Two suspended systems were needed to protect critical signalling and telecommunications cables while the existing railway bridge was removed and replaced. The wider programme was already under pressure from buried utilities and water-main works.

Working alongside Kier, Siemens, Phase Design & Engineering and other stakeholders, Pod-Trak applied its OLE, P-Way and Civils expertise to install steel foundations, erect the temporary structures, tension the cable supports and subsequently dismantle both bridges. Its integrated delivery approach helped protect railway assets and support critical construction milestones.

Quick Facts

Client Name
Kier
Project Location
Oxford, UK
Project Duration
2 Months

High Level Scope:

  • Installation of seven circular hollow-section (CHS) steel piled foundations.
  • Erection of structural steel columns, supports and anchorages.
  • Installation of east and west temporary suspended cable bridge systems.
  • Procurement and use of specialist high-capacity rigging and tensioning equipment.
  • Coordination of temporary signalling and telecommunications cable support.
  • Management of rail access, plant movements and bridge construction interfaces.
  • Engineering adjustments to maintain the required cable clearances.
  • Dismantling of both temporary bridges and cutting down accessible steel piles, with residual works coordinated.

Key Challenges & Solution

Restricted access, live railway interfaces and unexpected buried services created significant installation challenges. Pod-Trak worked with Kier and the design team to adapt foundation positions and construction sequencing as site conditions became clear.

The suspension system demanded cable tensions well beyond typical OLE applications. When initial equipment could not achieve the required geometry, the team sourced and deployed specialist six-tonne pulling equipment, enabling the necessary height and clearance.

Water-main delays and wider programme pressure made possession windows especially critical. Pod-Trak used its multidisciplinary workforce, experienced railway supervision and available plant resources to respond to changes, while pausing and replanning work whenever safety or equipment compatibility required it.

Innovation in Action

  • Integrated OLE, P-Way and Civils expertise enabled specialist temporary works delivery.
  • OLE piling, steelwork, rigging and tensioning techniques adapted to protect signalling cables.
  • Specialist six-tonne pulling equipment sourced to overcome exceptional loading demands.
  • Close collaboration with Kier, Siemens and the designer enabled rapid changes on site.
  • Safety-led possession decisions and controlled dismantling supported the wider bridge programme.