Align North Portal HS2 Works

Project Overview

Pod-Trak delivered a series of complex civil engineering packages for Align JV on the HS2 North Portal site in Great Missenden, Buckinghamshire. The £18m programme included large-scale earthworks, construction of reinforced concrete capping beams and cradle slabs, installation of 11,000m² of reinforced track slab, deep drainage, and a new on-site batching plant. Working within a live multi-contractor environment, Pod-Trak provided integrated design, engineering and delivery support to ensure each element was completed safely, efficiently, and to programme.

Quick Facts

Client Name
Align JV
Project Location
Great Missenden, Buckinghamshire
Project Value
£18m

High Level Scope:

  • Reinforced concrete capping beam and 300m-long cradle slab construction
  • 11,000m² reinforced concrete track slab installation
  • 700m of large-diameter drainage and manholes up to 8.5m deep
  • Full batching plant design and construction, including aggregate bins and platforms
  • Excavation, ducting, formwork, and utility connections

Key Challenges & Solution

The works were delivered under tight programme constraints, requiring precise coordination across multiple disciplines and contractors. Delays to the track slab start date prompted an accelerated delivery plan, introducing revised pour sequences, additional resources, and dual-shift working. Pod-Trak engineered bespoke shoring for deep drainage, maintaining headwall stability while safeguarding adjacent operations. Close collaboration with Align JV, proactive logistics planning, and staged handbacks ensured critical HS2 milestones were achieved on time.

Innovation in Action

Pod-Trak deployed its full in-house plant capability, reducing reliance on external resources and optimising sequencing between civils, drainage, and batching operations. Innovative “slide rail” shoring technology was used for deep drainage, improving safety and productivity by eliminating vibration and reducing lifting operations. The on-site batching plant was designed and constructed with sustainable methods, including prefabricated reinforced walls, legato block construction, and advanced power-floated finishes. These innovations enhanced quality, reduced carbon impact, and improved delivery efficiency across the entire programme.