South Tottenham Bridge

Description

Expertise: Permanent Way
Value: £260k

This project involved the replacement of South Tottenham road bridge; Pod-Trak were contracted to complete the Permanent Way works which included:

• Off-site build-up of track panels on the new bridge deck

• The strip-out of the existing layout

• The installation of the layout upon completion of the bridge installation • Stressing of all effected surrounding infrastructure

The works were successfully delivered on time with no follow up works required; the delivery proved challenging due to adverse weather conditions over the Christmas blockade period.

  • Project Duration : Christmas Blockade 2014
  • Categories : PWay
  • Client : VolkerFitzpatrick