Expertise: OLE
Value: £500k

OLE modifications to facilitate the installation of a new train wash. Works included the installation of new structures, SPS, headspans, section insulators, wiring and registration. Redundant OLE was stripped out and returned to the maintainer. Following completion of the installation and removal works the OLE testing and commissioning took place and handback documentation was completed and returned.

  • Project Duration : December 2015 to July 2016
  • Categories : OLE
  • Client : C Spencer Ltd