Ilford Crossrail Depot Works

Description

Expertise: OLE, Civil Engineering
Value: £9.6m

Pod-Trak are contracted to complete all the OLE and Civils Works for the Ilford Crossrail Depot. These works included:

• The removal of old and installation of new OLE equipment at the Depot
• Registration of OLE works

• All Civil works, including reduced level dig, backfill, ballast to bottom of sleepers, walkways, troughing routes, storm water track drainage, foul water drainage, bases, slabs, lighting, UTX’s and ancillary works.
• Works undertaken in two phases:-Blockade in live depot from 6th August until 4th December 2016 High Street Environment / Possessions from 5th December onwards

  • Project Duration : August 2016 - April 2017
  • Categories : Civils, OLE
  • Client : Volker Fitzpatrick