Ardwick Traincare Depot (Siemens)

Description

Expertise: Electrification / OLE
Value: £1.2m

Pod-Trak were contracted to supply and install all OLE required to electrify the Siemens operated depot at Ardwick in Manchester including the tie-in to the mainline. The existing track layout was a single connection from the Up East line to the single Ardwick Reception Siding,which provides the connection to the facility. This arrival line was wired to enable the passage of electric rolling stock into Ardwick Train CareDepot from Manchester Piccadilly.
With careful planning and communication between Pod-Trak, Spencer Group and Siemens, the Depot remained operational throughout the installation programme.

  • Project Duration : January 2013 - July 2013
  • Categories : OLE
  • Client : C Spencer Ltd